Royal Inland Hospital: Patient Care Tower Project

Request: DIC-23012


Royal Inland Hospital: Patient Care Tower Project

Call Out Date: Next Business Day After Posting
Start Date:

Request Received:
Contractor: ESC Automation, Houle (other)
Location:
LOA/Camp/LH:
Hire Region:
Agreement: Inside Electrical Workers Collective Agreement
Shift:
Hours:
Duration: Contractor did not specify
Manpower Requested:
Type of Work:
Additional Information:

On July 10, 2015, the Patient Care Tower Project was approved at Royal Inland Hospital (RIH). 

 The project will be constructed in two phases.

  • Phase I includes the construction of a new patient care tower with two levels of underground parking.
  • Phase II includes renovations to the existing hospital building.

Timeline

Construction on Phase I is expected to begin in fall 2018 and be completed by spring 2022, at which time construction will begin on Phase II. Phase II construction is expected to be completed by 2024 (according to Interior Health).

Saftey

Face masks are mandatory full-time for all workers at the Hospital.

Register for this Request