Houle (other)

Houle (other)

  • Site C Dam

    Request: DIC-22386


    Site C Dam

    Call Out Date: Next Business Day After Posting
    Start Date:

    Request Received:
    Contractor: F&M Installations, Houle (other), Voith Hydro
    Location:
    LOA/Camp/LH:
    Hire Region:
    Agreement: Project Agreement
    Shift:
    Hours:
    Duration: Contractor did not specify
    Manpower Requested:
    Type of Work:
    Additional Information:

    The Site C Dam is a project of BC Hydro for a large-scale earth fill hydroelectric dam on the Peace River near Fort St. John in northeastern British Columbia, Canada. The site is downstream from the existing W.A.C. Bennett and Peace Canyon dams. Designs call for an estimated peak capacity of approximately 1,100 MW, average output of 900 MW, and an annual output of 5,100 GWh of electricity. When completed, Site C will be the first large dam built in BC since 1984 and BC’s fourth largest producer of electricity.

    Site C Evacuation Protocol Document
    You can download the Evacuation Protocol Document from the Site C Downloads section of this website.

    Turbines and Generators

    Voith & F&M Installations

    Schedule

    F&M Installations: 19 Days on and 9 days off, 10  Hours per day
    Voith: 21 Days on and 7 Days off, 10 Hours per day

    Wages

    The workday shall be ten (10) hours with all hours paid at one point three-five times
    (1.35X) the otherwise applicable straight time hourly rate as stated in the current Wage Schedule.

    Agreement

    The FINAL SPNA for Site C Turbines and Generators agreement is available along with other documents in the Job Related Downloads linked below.

    Balance of Plant

    F&M Installations & Houle

    Schedule

    14 Days on and 7 Days off, 10 Hours per day

    Wages

    The workday shall be ten (10) hours with all hours paid at one point two-eight times
    (1.28X) the otherwise applicable straight time hourly rate as stated in the current Wage Schedule.

    Nights

    There is a $4/hr premium for night shift.

    Agreement

    The Site C Clean Energy Project – Generating Station and Spillway Balance of Plant agreement is available along with other documents in the Job Related Downloads linked below.

    Register for this Request